




Construction Program
I-295 Interchange
![]()
Construction Contracts:
Adjustments may be made depending upon funding, schedule and final design. Final information will be available on MSHA’s website.

For a graphical summary of the contracts
for Maryland see Project
Overview or
Construction Program Overview / Schedule
Graphics.
| Contract Description | Est. Value $M |
Status of Advertisement |
Approximate Duration (months) |
|
| 1A | Rosalie Island pre-consolidation, including mass grading, pre-consolidation of existing soils, and retaining walls. Work includes installation of wick drains, earth surcharge and high strength geotextiles at MD abutment. Project No. PG 3555173 |
Actual $9.4M |
Contract Completed | |
| 1. | Ramps to/from S-curve connection. Replacement of S-curve ramps with new longer bridges to permit future construction of Outer Loop Local and Express lanes. Work includes access to Oxon Hill Rd. Includes 6 bridges and 4 retaining walls. Project No. PG 3465173. |
Actual $42M |
Completed March 2006 |
31+ |
| 2/3 | Outer Loop Express and Local Lanes, ramps under I-95, including lightweight fill behind the MD abutment. Ramps over I-95 and National Harbor Interchange. Includes 11 bridges and 10 retaining walls. Project No. PG 3475173. |
Actual $45.3M |
Completed July 2006 |
42+ |
| 4/6/7 | Inner Loop Express and Local Lanes, and balance of most ramps and I-295 and a portion of the I-95 median. Includes 7 bridges and 7+/- retaining walls. Rosalie Island Deckover (bridge + approach walls + park) Landscaping at I-295 Interchange Project No. PG 5025173. |
Actual $93.2M |
Construction Underway |
60+ |
| 5. | HOV Ramps to D.C. (likely to be deferred; I-295 Contract 5). | $25M
-
$30M ($2001) |
TBD | 24+ |