Construction Program
Telegraph Road Interchange
![]()
Anticipated Construction Contracts:
The preliminary information below reflects adjustments made due to the availability of funds resulting from contract bids coming in under estimate. Final information will be provided on VDOT's web page.

For a graphical summary of the contracts
for Maryland see Project
Overview or
Construction Program Overview / Schedule
Graphics.
| Contract Description | Est. Value $M |
Status of Advertisement |
Approximate Duration (months) |
|
| VB 1 | Advanced ITS Contract. Project No. 0095-96A-106/105, C505 |
Actual $1.53M* |
Completed April 2004 |
|
| VB 2/3/6 | Reconstruct I-95 mainline form the Eisenhower Connector to meet VA6/7 including interchange ramps and bridges over Cameron Run, telegraph Road and CSX/Southern/ WMATA. Utility relocations, noise walls, pedestrian paths, pavement reconstruction, traffic systems, lighting, signage, landscaping and Cameron Run wetland mitigation | $225M ($2005) | Advertised Aug 28 , 2007 |
48+ |
| VB 4 | VA Ground Improvement contract utilizing wick drain soil consolidation, excavation, use of lightweight backfill, utility relocation and storm drainage. Project No. 0095-96A-105 | Actual $2.98M |
Completed January 2006 |
27+ |
| VB 5 | Telegraph Road advance utilities, relocate utilities , building demolition, rough grade for Burgundy Rd. Project No. 0095-96A-105, C512 |
Actual $18M |
Construction Underway |
24+ |
| * Combined with VA9 for complete work through the US Route 1 and Telegraph Road interchanges ** Potential for Phased Construction based upon available funding |
||||