Construction Program with Status Print E-mail

Construction Contracts:

Contract specific advertisement dates and bid results are available on VDOT's web page.

Rendering of new U.S. Route 1 Interchange

For a graphical summary of the contracts for Maryland see Project Overview or
Construction Program Overview / Schedule Graphics.

 

Contract Description Est. Value
$M
Status of
Advertisement
Approximate
Duration
(months)
VB 1 Advanced ITS Contract.
Project No. 0095-96A-106/105, C505
Actual
$1.53M*
Completed
April 2004
VB 2/3/6
Reconstruct I-95 mainline form the Eisenhower Connector to meet VA6/7 including interchange ramps and bridges over Cameron Run, telegraph Road and CSX/Southern/ WMATA. Utility relocations, noise walls, pedestrian paths, pavement reconstruction, traffic systems, lighting, signage, landscaping and Cameron Run wetland mitigation $225M
($2005)
Advertised
Aug. 28, 2007
48+
VB 4
VA Ground Improvement contract utilizing wick drain soil consolidation, excavation, use of lightweight backfill, utility relocation and storm drainage. Project No. 0095-96A-105 Actual
$2.98M
Completed
January 2006
27+
VB 5
Telegraph Road advance utilities, relocate utilities , building demolition, rough grade for Burgundy Rd.
Project No. 0095-96A-105, C512
Actual
$18M
Construction
Underway
24+

* Combined with VA-9 for complete work through the U.S. Route 1 and Telegraph Rd Interchanges

** Potential for Phased Construction based upon available funding.