Construction Program with Status |
|
|
Construction Contracts:
Contract specific advertisement dates and bid results are available on VDOT's web page.

For a graphical summary of the contracts for Maryland see Project Overview or Construction Program Overview / Schedule Graphics.
| Contract Description |
Est. Value $M |
Status of Advertisement |
Approximate Duration (months) |
| VB 1 |
Advanced ITS Contract. Project No. 0095-96A-106/105, C505 |
Actual $1.53M* |
Completed April 2004 |
|
VB 2/3/6
|
Reconstruct I-95 mainline form the Eisenhower Connector to meet VA6/7 including interchange ramps and bridges over Cameron Run, telegraph Road and CSX/Southern/ WMATA. Utility relocations, noise walls, pedestrian paths, pavement reconstruction, traffic systems, lighting, signage, landscaping and Cameron Run wetland mitigation |
$225M ($2005) |
Advertised Aug. 28, 2007 |
48+ |
VB 4
|
VA Ground Improvement contract utilizing wick drain soil consolidation, excavation, use of lightweight backfill, utility relocation and storm drainage. Project No. 0095-96A-105 |
Actual $2.98M |
Completed January 2006 |
27+ |
VB 5
|
Telegraph Road advance utilities, relocate utilities , building demolition, rough grade for Burgundy Rd. Project No. 0095-96A-105, C512 |
Actual $18M |
Construction Underway |
24+ |
|
* Combined with VA-9 for complete work through the U.S. Route 1 and Telegraph Rd Interchanges
** Potential for Phased Construction based upon available funding.
|
|
|