Construction Program with Status Print E-mail

Construction Contracts:

Adjustments may be made depending upon funding, schedule and final design. Final information will be available on MSHA’s website.

Rendering of new I-295 Interchange

For a graphical summary of the contracts for Maryland see Project Overview or
Construction Program Overview / Schedule Graphics.

 

Contract Description Est. Value
$M
Status of
Advertisement
Approximate
Duration
(months)
1A. Rosalie Island pre-consolidation, including mass grading, pre-consolidation of existing soils, and retaining walls. Work includes installation of wick drains, earth surcharge and high strength geotextiles at MD abutment.
Project No. PG 3555173
Actual
$9.4M
Contract
Completed
1. Ramps to/from S-curve connection. Replacement of S-curve ramps with new longer bridges to permit future construction of Outer Loop Local and Express lanes. Work includes access to Oxon Hill Rd. Includes 6 bridges and 4 retaining walls.
Project No. PG 3465173.
Actual
$42M
Completed
March 2006
31+
2/3 Outer Loop Express and Local Lanes, ramps under I-95, including lightweight fill behind the MD abutment. Ramps over I-95 and National Harbor Interchange. Includes 11 bridges and 10 retaining walls.
Project No. PG 3475173.
Actual
$45.3M
Completed
July 2006
42+
4/6/7 Inner Loop Express and Local Lanes, and balance of most ramps and I-295 and a portion of the I-95 median. Includes 7 bridges and 7+/- retaining walls.

Rosalie Island Deckover (bridge + approach walls + park)

Landscaping at I-295 Interchange

Project No. PG 5025173.
Actual
$93.2M
Construction
Underway
60+
5. HOV Ramps to D.C. (likely to be deferred; I-295 Contract 5). $25M - $30M ($2001) TBD 24+