Construction Program with Status |
|
|
Construction Contracts:
All contracts for the Woodrow Wilson Bridge have either been rewarded or are currently under construction.

For a graphical summary of the contracts for Maryland see Project Overview or Construction Program Overview / Schedule Graphics.
| Contract Description |
Est. Value $M |
Status of Advertisement |
Approximate Duration (months) |
| 1. |
Bridge Contract 1- Initial Dredging Project No. PG 3405173 |
Actual $14.5M |
Completed February 2001 |
|
| 2. |
Bridge Contract 2- Foundation contract Excludes VA and MD abutment. Project No. PG 3415173 |
Actual $125M |
Completed June 2003 |
|
| 3. |
Bridge Contract 3A - Bascule Spans, Bascule Piers, portion of Superstructure and Operator's Tower Project No. PG 3455173R |
Actual $185.9M |
Under Construction |
66+ |
|
Bridge Contract 3B - Virginia approach spans. Project No. PG 5175173 |
Actual $115.5M |
Under Construction |
64+ |
|
Bridge Contract 3C - Maryland approach spans. Project No. PG 5155173 |
Actual $191.1M |
Under Construction |
61+ |
|
|