Construction Program with Status Print E-mail

Construction Contracts:

Contract specific advertisement dates and bid results are available on VDOT's web page.

Rendering of new U.S. Route 1 Interchange

For a graphical summary of the contracts for Maryland see Project Overview or
Construction Program Overview / Schedule Graphics.

 

Contract Description Est. Value
$M
Status of
Advertisement
Approximate
Duration
(months)
1. US Army Reserve Center Demolition.
Project No. 0095-100-104,N506
Actual
$110,075
Completed
November 2000
2. Ground Improvement Contract between US Route 1 and Telegraph Road Interchange.
Project No.. 0095-96A-106,
C503, D651
Actual
$34.4M
Completed
April 2004
3. Demolition of Hunting Tower and 2 garages.
Project No. 0095-100-104,C510
Actual
$988,000
Completed
April 2004
4. US Route 1 Tie-In Contract provides 6-lane tie-in to completed (OL) Woodrow Wilson Bridge. Includes reconstruction of Washington St bridge, urban deck and demolition of 3 Hunting Terrace buildings and 2 office buildings. Construct retaining walls and noise walls; relocate utilities; reconstruct Hunting Towers/Terrace Parking; provide memorial to Freedman's Cemetery. Construction of West Abutment of Woodrow Wilson Bridge.
Project No. 0095-96A-106, B648-50, C504, C511, L802
Actual
$54.4M
Construction
Underway
72+
5. US Route 1 Interchange Contract including Outer Loop low level / high level bridges mainline and ramp connections.
Project No. 0095-96A-106,C520
Actual
$38.3M
Completed
September 2005
24+
5A Pile Indicator Program Actual
$664,250
Completed
January 2003
6/7 US Route 1 Interchange Contract including Inner and (OL) roadway mainline. Construct remaining bridges and interchange ramps, mainline roadway pavement, ground improvement, noise barriers, drainage systems, utility relocations, traffic systems, signs, roadway lighting and landscaping. Reconstruct and widen US Route 1 from Fort Hunt Road to Huntington Avenue. Project No. 0095-96A-106,C501 Actual $146.6M Construction
Underway
66+
8. Jones Point Park improvements. Pending.
Project No. TBD
TBD TBD TBD
9. Virginia advanced ITS contract. Project No. 0095-96A-106 / 105, C-505 Actual
$1.53M *
Completed
April 2004
* Combined with VB-1 for complete work through the U.S. Route 1 and Telegraph Rd Interchanges