Contract Description Est. Value
$M
Status of
Advertisement
Approximate
Duration
(months)
1/2 Early phase construction for noise / retaining walls for Inner Loop, landscaping / mitigation at Flintstone Elementary School. Bald Eagle Road, ramp bridge over Oxon Hill Road, ramp connections to Outer Loop, retaining walls, ramp connections to Oxon Hill Road. Oxon Hill Road, noise barrier at Forest Heights Baptist Church. Actual
$18.7M
Completed
June 2006
24+
3 MD 210 bridge over Beltway, Oxon Hill Road grade separation, MD 210 roadways; includes a new communication tower and relocation of the MSHA salt barn. Actual
$44.2M
Construction
Underway
30+
4 Inner Loop and Inner Loop / Beltway ramps west of Livingston Road, bridge over Livingston Road, retaining wall for north side of HOV lanes, and temporary pavement for cross over. Outer Loop express and bridge over Livingston Road, HOV Ramps, Ramp B bridge and mainline paving.
(Defers Livingston Rd. bridge, mainline east of this bridge, HOV and most of outerloop)
Actual $59.4M Construction
Underway
36+